Tests for the Alpha Test

The numbers in this spreadsheet are in reference to the Alpha Test Document.

Each AlphaTestStations should perform as many of these tests as possible. Some tests are not applicable to some stations, in cases where the local hardware capabilities do not exist. In those cases please add "n/a" in the field. G-SYS will review each row periodically and make it clear when a test has been completed by enough stations.

Test AAU Dave G3VZV KU CalPoly ESTEC AUS Schedule SYS Review SYS Comments
GT01 Failed - ASAP - Autonomous Re-written, WS-VI
GT02 Failed - ASAP - Autonomous Re-written, WS-VI
GT03 Failed - ASAP - Autonomous Re-written, WS-VI
GT04 Not tested yet - ASAP - Autonomous Re-written, WS-VI
GT05 Not tested yet - ASAP - Autonomous Re-written, WS-VI
GT06 Not tested yet -
MT01 Not tested yet - ASAP - Autonomous Re-written, WS-VI
MT02 Not tested yet - ASAP - Autonomous
MT03 Not tested yet - ASAP - Autonomous
MT04 Not tested yet - ASAP - Autonomous Re-written, WS-VI
AT01 - - - - - - Done since Workshop 5 Complete Pending
AT02 - - - - - - Done on workshop 5 Complete Pending
AT03 - - - - - - Done on and since workshop 5 Complete Pending
AT04 - - - - - - Requires an (alpha) final XSD
AT05 - - YES - - - Done on workshop 5 Complete
AT06 - - - - - - Requires MCC report download function
AT07 - - YES - - - Done on and since workshop 5 Complete
AT08 - - - - - - Requires CA and API in place
AT09 - - - - - - Requires CA and API in place
AT10 - - - - - - Requires Clustering decided, designed an in place
ST01 Not tested yet To be coordinated Re-written, WS-VI
ST02 Not tested yet To be coordinated Re-written, WS-VI
ST03 Not tested yet To be coordinated Re-written, WS-VI
ST04 Not tested yet To be coordinated Re-written, WS-VI
ST05 Not tested yet To be coordinated Re-written, WS-VI
ST06 Not tested yet To be coordinated Re-written, WS-VI
ST07 Not tested yet To be coordinated Re-written, WS-VI
ST08 Not tested yet To be coordinated Re-written, WS-VI